CAUTION:
•
Commissioning and start-up of the heat pump must be supervised by a qualified refrigeration qualified
technician.
•
Start-up and operating tests must be carried out with a thermal load applied and water circulating in the
water heat exchanger.
•
All set point adjustments and control tests must be carried out before the unit is started up.
Ensure that all safety devices are operational, especially that the high pressure switches are functioning on and
that any alarms are acknowledged.
Note:
If the Manufacturer instructions (power and water connections and installation) are not observed, the
Manufacturer warranty becomes invalid.
System Start Up:
Start the system in heating mode. Check the following parameters during the test and ensure that no error codes
are generated during the start-up test.
Date / Hour
Air
Outdoor Air Temp (°C)
P001
Water
Entering Water Temp (°C)
P003
Leaving Water Temp (°C)
P004
Water Control Temp (°C)
P052
Suction
Saturated Suction Temp (°C)
P008
Suction Temperature (°C)
P009
Superheat Temperature (°C)
P015
Superheat Target Temp (°C)
P016
Discharge
Discharge Temperature (°C)
P010
Refrigerant Temperature (°C)
P005
Compressor
Requested Compressor Frequency (Hz)
P022
Actual Compressor Frequency (Hz)
P023
Water control
Water Control Point (°C)
P051
Flow Switch Status
P105
Safety Switch Status
P104
Water
pressure /
flow rate
Entering water heat exchanger pressure (kPa)
-
Leaving water heat exchanger pressure (kPa)
-
Pressure drop (without internal pump)(kPa)
-
Flow rate from curves (without internal pump) (l/sec)
-
Or available external pressure (with internal pump) (kPa)
-
Flow rate from curves (with internal pump) (l/sec)
-
Power
Network Voltage (V)
-
Input Amperage (A)
-
Repeat the above test with the heat pump system operating in cooling mode and DHW mode.