AMI Hydrazine
Maintenance
A-96.250.501 / 280915
47
6.9.3
Process Hydrazine
The sample must always overflow into the longer overflow tube of
the constant head. Only perform process calibration if the differ-
ence is significant.
Grab sample
Take a grab sample directly from the flow cell. Open the grab sam-
ple valve and drain water for a minute before taking the sample.
Observe the displayed value of the AMI Hydrazine while taking the
grab sample. The measuring value has to be stable.
Determine the hydrazine concentration of the sample by manual
analysis.
Compare the result with the measuring value of the AMI Hydrazine.
If the measuring value of the AMI Hydrazine has changed while
performing the manual analysis, enter the difference between the
measuring values of the AMI Hydrazine.
Example
Displayed measuring value of AMI Hydrazine during grab sample:
10 ppb
Displayed measuring value of AMI Hydrazine after concentration
determination: 15 ppb.
Determined hydrazine concentration: 8 ppb
There is a change of the measurement value of 50% during the
concentration determination. This means, you have to correct the
determined hydrazine concentration also with a factor of 50%.
This will result in a value of 8 ppb + (50% of 8 ppb) = 12 ppb
Finally, you have to enter 12 ppb as a process value at the AMI
transmitter
Example of
Process
Calibration
1
Navigate to menu
<Maintenance>/<Calibration>.
2
Press [Enter]
1
Select Process Hydrazine
2
Press [Enter]
3.1
Calibration
Simulation
Maintenance
Set Time 01.01.05 16:30:00
Calibration
3.1.1
Calibration
Zero Hydrazine
Process Hydrazine