HRX-OM-M005
Chapter 3 Transporting and Installation
HRZD Series
3.3 Procedure for Installation
3-9
3.3.4
Procedures for wiring installation
1.
Turn OFF the power breaker on customer side (primary side), and then use the assigned
procedures to peform lockout/tagout.
[Tips]
Connection of the power cable with the product must be established first.
Do not connect the cable with the factory side at this point.
2.
Turn OFF the main breaker of the product.
3.
Undo the screws (2 pcs.) to open the front door.
Front
Front door
Screw
OFF
Main breaker OFF
Figure 3-6 Main Breaker OFF
Be sure to turn OFF the factory side (primary side) power before
connection to the product.
Use the assigned procedure to peform lockout/tagout (Page 1-10).
Содержание HRZD020-W1S-W1S
Страница 24: ...HRX OM M005 Chapter 2 Name of Each Section 2 1 Name of Each Section HRZD Series 2 2 ...
Страница 44: ...HRX OM M005 Chapter 4 Product Startup and Shutdown 4 5 Product Startup and Shutdown HRZD Series 4 6 ...
Страница 98: ...HRX OM M005 Chapter 5 Product Operation 5 3 Operation Screen HRZD Series 5 54 ...
Страница 128: ...HRX OM M005 Chapter 8 Appendix 8 8 Thermo Chiller Daily Inspection Sheet HRZD Series 8 20 ...