Instruction Manual OilGuard Ex M
10241E/2
7
3
Installation & commissioning
3.1
Installation of the Photometer
The following procedure has proven to be reliable when installing a measuring
point:
Action
1.
Remove the photometer from the packaging.
2.
Attach the photometer horizontally to the
intended location.
3.
Make sure that the supplied purge air line is
attached to the measuring cell and to the
pressure regulator.
4.
Attach the purge air (arrow).
The purge air must be clean, dry and free
of oil (instrument air).
5.
Assemble the supplied measuring cell.
→
Section 3.1.2
6.
Attach the components for sampling
(
→
Section 3.1.1).
3.1.1
General information about measuring cell installation
For the sample connections lightproof hoses and lines have to be used.
The sampling must be designed so that representative quantities are
supplied to the photometer.