Siemens-Elema AB
SPS-UD
RX B7-120.033.01.10.02
MAMMOMAT 300
Solna, Sweden
05.98
65 02 186
1-2
Prerequisites
Start-up, DHHS and X-ray decree area of application
Important notes on start-up
The MAMMOMAT 300 is adjusted, programmed and tested in the factory, leaving only
the adaption to the on-site mains voltage and the functional tests to be performed.
When the measurements to be made (kV, mAs, etc.) are within the tolerances stated in
these instructions, this confirms that the settings made in the factory have not changed and
the equipment is fully serviceable.
The measured values marked with >> in section 11 shall be entered in the test certificate
provided.
The service PC is required only for programming according to:
•
Section 11, Checks with high voltage
•
Section 12, Start-up and functional test of the Iontomat
Programming the "Correction curve"
Setting the "sensitivity" (film density)
Setting the "sensitivity correction" (adaption to different exposure techniques)
•
Section 13, Further programming
•
Section 19, Final procedures
Recording the programmed values.
Reading the exposure counter and deleting the error memory.
NOTE!
If the generator is switched off with the Service PC connected, wait approximately 5 sec-
onds before switching it on again.
Checking and recording for the area of application of the X-ray decree
(§16 Germany)
In the area of application of the X-ray decree, an acceptance test certificate is supplied,
with most of the data filled in by the factory.
Only:
•
the cut-off dose
•
the resolution of the film/screen systems used, and
•
the output values of the constancy test
must be determined by the owner of the equipment and recorded in the acceptance test
certificate. Furthermore, the front page of the acceptance test certificate must also be com-
pleted with the operator´s data.