Installation | 7
63/174
500-8384.9 • Version 11 • Installation and Operating Instructions • 8DJH
6.
Only for panels in wall-standing arrangement (except metering panels):
Fasten the top
unit for the pressure relief duct using 8 bolt-and-washer assemblies.
8x
Fig. 47:
Mounting the top unit
7. Bolt the cable bracket
1
, the adjustment rail and the cable clamps together using 4 self-
tapping bolts M6 (tightening torque: 12 Nm).
4x
4x
Fig. 48:
Mounting the cable bracket (ring-
main panel)
Fig. 49:
Mounting the cable bracket
(transformer panel)
Page 126, "Removing and mounting the cross member"].
9. Hook the cable compartment cover in [
Page 125, "Removing and mounting the cable
10. From now, the high-voltage cables can be mounted.
11. Seal the joint between the switchgear and the base all around with silicone.
Fig. 50:
Sealing the joint
1
Switchgear
2
Panel joint
3
Base