ASSEMBLY
6
6.4
Installation sequence
Installation is carried out according to the sequence in this Section, the sender/receiver
unit is not installed until commissioning.
NOTICE:
Device damage due to premature installation of the measuring device on the
gas duct
Unsuitable ambient conditions or the atmosphere in the measuring duct can damage
the measuring system and make intended use impossible.
▸
The sender/receiver unit is first positioned in the duct during commissioning (
“Fitting and connecting the sender/receiver unit”, page 66
).