Appendix A:
Assembly of Split Units
Purpose
To provide an overview and basic
understanding of the process for on-site
assembly of split air handling units.
Installer Supplied Tools and Material
• Exterior-grade caulking
• Rigging equipment sufficiently rated
for the weights being hoisted
• Sufficiently long threaded rod, nuts
and bolts to pull sections together
• Soapy water to lubricate between
the roof curb and unit base (if
required)
• Come-alongs (only to be used on
the base frame as needed)
Factory Supplied Material
• Neoprene gasket
• Roof caps
• Fasteners
Instructions
These instructions apply to both
vertically and horizontally split units. All
joining hardware is provided by Price
Industries and is shipped with the unit
unless noted otherwise.
1. Ensure the bottom of the first
section’s base is clean and free
from debris and place it on the roof
curb, aligning all edges. Connect
and tighten the fasteners holding
the section to the roof curb if
applicable.
2. Sections with 6-point lifts may have
removable center lugs (Figure 1).
They can be removed once the
section is seated on the roof curb.
FIGURE 1: REMOVABLE CENTER LUG SHOWN ON BASE FRAME
Содержание AW-I Series
Страница 37: ...35 AW I NOTES priceindustries com AW I Manual...
Страница 38: ...36 AW I NOTES AW I Manual priceindustries com...
Страница 39: ...37 AW I NOTES priceindustries com AW I Manual...