Troubleshooting
110
Troubleshooting Using Standard Test Equipment
Table 34 describes basic troubleshooting methods using standard test equipment.
Table 34. Troubleshooting Using Standard Test Equipment
Indication
Problem
Action
No HDSL Loop Sync
HDSL wire pair is impaired.
(too long, open, shorted, or grounded)
See Table 35, “12/24 Channel HDSL
Transmission Distance,” on page 111
Use the local practices to test the wire pairs.
No power to the RT
The tip and ring voltages are incorrect.
Measure the voltage from T1 to frame ground
and from R1 to frame ground. This should be a
positive voltage up to +130 Vdc.
Measure the voltage from T2 to frame ground
and from R2 to frame ground. This should be a
negative voltage down to -130 Vdc.
The HDSL voltages are incorrect
Measure the voltage from T1 to frame ground
and from R1 to frame ground. This should be a
positive voltage up to -130 Vdc.
Measure the voltage from T2 to frame ground
and from R2 to frame ground. This should be a
negative voltage down to +130 Vdc.
No dial tone
Move or swap cards to isolate the defective unit.
No dial tone for all
systems
Check for MAJOR alarm, this terminates dial
tone to the RT.
Check the alarm history.
If still no dial tone and no major alarms, verify
that the channels are not disabled. Refer to
“Channel Configuration.”
No ring on one channel
Swap cards.
No ring on all channels
Check for a major alarm on the FPI-729 or
FAU-728 front panels.
If yes, replace the channel unit.
If no, check for a dial tone.
Note: The ring generator is on the line unit, not
the channel unit.
“Popping” intermittent
dial tone (POTS only)
Service disconnects or Major Alarms
If using an FAU 728 List 2 or and FPI-729 List
1, verify that the composite clock is terminated.
(Refer to “Connect the Composite Clock” on
page 46.)
Содержание PG-Flex
Страница 10: ...PG Flex System Overview 2 Figure 1 Typical PG Flex Configuration 23 Shelf shown ...
Страница 24: ...PG Flex System Overview 16 ...
Страница 44: ...Installing PG Flex System Hardware 36 Figure 16 Line Unit and Channel Unit Installation Locations ...
Страница 52: ...Installing PG Flex System Hardware 44 Figure 21 Connecting the Metallic Bypass Pair ...
Страница 62: ...Installing PG Flex System Hardware 54 ...
Страница 66: ...Terminal Management 58 Figure 28 Connecting an ASCII Terminal to a Line Unit ...
Страница 104: ...Performance Monitoring 96 ...
Страница 120: ...Troubleshooting 112 ...
Страница 158: ...Screen Menus and Definitions A 36 ...
Страница 162: ...Acronyms and Glossary Glossary 4 ...
Страница 167: ......
Страница 168: ......