Commissioning Checklist
ALL work MUST be carried out by technically trained competent personnel.
Pre Commissioning checks
Pressure test
Ensure that the system has been pressure tested for pipework integrity and leaks. This not only ensures a correctly
operating system but also reduces potential leaks in the future.
Electrical Connections
Prior to turning on the power supply to the unit ensure that all electrical connections are tight and correctly terminated.
External Fuses/MCBs
Check that the correct electrical supply rating is available to the unit.
Electrical Continuity
Before electrical power is applied to the unit, electrical continuity must be carried out on the 3 phase power.
Phase Rotation
Check that the phase rotation is correct. Components in the unit will malfunction with incorrect phase rotation. Check
with a phase rotation meter.
Electrical Earthing
Check that the earth is correctly bonded.
Remote ON/OFF
To ensure that the unit does not start doing the pre-commissioning checks the remote on/off should be in the OFF state.
Measure the voltage at the following points and record on the commissioning sheet:
● Mains incoming
● Dedicated power supply
● Permanent supply
● Control voltage at the transformer (min 22.5V, max 25V)
Commissioning Procedure
General
To be read in conjunction with the commissioning sheets provided.
Please ensure all documents have been completed correctly and return to Airedale Technical
Support immediately to validate warranty.
NOTE
The equipment contains live electrical and moving parts, ISOLATE prior to maintenance or repair
work.
WARNING
The unit shall be commissioned with the return air dew point above the water inlet temperature to prevent condensation
build up on any unit pipework without pipework lagging.