Lifting
Whenever the unit is lifted, it should be from the base and, where possible, with all packing and protection in position. If
any type of slinging is used, due care should be taken to ensure that the slings do not crush the casework.
● Employ lifting specialists.
● Local codes and regulations relating to the lifting of this type of equipment should be observed.
● Use the lifting eye bolts provided.
● Attach lifting chains to the lifting eye bolts provided. Half the number of lifting points must be capable of lifting the
whole unit.
● Use the appropriate spreader bars/lifting slings with the holes provided.
● Lift the unit slowly and evenly.
● If the unit is dropped, it should immediately be checked for damage.
Packed Dimensions
Single slab units may be shipped mounted on a wooden pallet and covered with polythene. The pallet shall be
mechanically fixed to the unit for transportation only. The packaging adds 50mm (2”) to the length and width of the unit
and 160mm (6.3”)to it’s height. Please contact Airedale for this option.
WIDTH + 50mm (2in)
DEPTH + 50mm (2in)
HEIGHT
+ 160mm (6.3in)
Installation Data
Unpacking
The unit is to be carefully unpacked, inspected and any damage reported to Airedale immediately.
All packaging is to be recycled accordingly.
1. The floor stand shall be lifted off the shipping pallet using appropriate lifting equipment such as skoots, under the
external side rails.
Positioning and Installation
IF FORKLIFT IS USED ENSURE
THE FORKS FALL AS CLOSE AS
POSSIBLE TO THE CROSS RAILS
FOR STRENGTH