- 154 -
[
VII
Control ]
-9- Refrigerant Recovery Control <PUHY>
Recovery of refrigerant is performed during heating operation to prevent the refrigerant from accumulating inside the unit
while it is stopped (unit in fan mode), or inside the indoor unit that is in cooling mode or in heating mode with thermo off. It
is also performed during cooling operation to prevent an excessive amount of refrigerant from accumulating in the outdoor
heat exchanger.
It is also performed during cooling operation to prevent an excessive amount of refrigerant from accumulating in the outdoor
heat exchanger.
(1) During heating operation
[Starting refrigerant recovery mode]
The refrigerant recovery mode in heating starts when all of the following three conditions are met:
15 minutes have passed since the completion of previous refrigerant recovery.
Td > 115°C [239°F]
Frequencies below 50 Hz
[Refrigerant recovery]
1) Refrigerant is recovered with the LEV on the applicable indoor unit (unit under stopping mode, fan mode, cooling,
heating with thermo off) being opened for 30 seconds.
2) Periodic capacity control of the outdoor units and periodic LEV control of the indoor units will be suspended during
refrigerant recovery operation; they will be performed after the recovery has been completed.
3) Defrost operation will be suspended until refrigerant recovery has been completed.
(2) During cooling operation
[Starting refrigerant recovery mode]
The refrigerant recovery mode starts when all the following conditions are met
30 minutes have passed since the completion of previous refrigerant recovery.
When the unit keeps running for 3 minutes in a row or more with high discharge temperature
Td > 105°C [221°F] or
Pd > 3.43 MPa [497 psi] (35 kg/cm
2
G) and SC0 > 10 deg°C [18 deg°F]
[Refrigerant recovery]
Increase the opening of LEV1 (Periodic control begins when 30 seconds have elapsed).
-10- Refrigerant Recovery Control <PURY>
Recovery of refrigerant is performed during heating operation to prevent the refrigerant from accumulating inside the unit
while it is stopped (unit in fan mode), or inside the indoor unit that is in cooling mode or in heating mode with thermo off.
It is also performed during cooling operation to prevent an excessive amount of refrigerant from accumulating in the outdoor
heat exchanger.
[Starting refrigerant recovery mode (during cooling only, cooling main, heating only, or heating main operation)]
The refrigerant recovery mode starts when all of the following conditions are met:
1) When 15 minutes have past in heating only or heating main mode or 5 minutes have passed in cooling only or
cooling main mode since the completion of previous refrigerant recovery
P72-P144: Td > 105°C [221°F]
P168-P234: Td1 > 105°C [221°F] or Td2 > 105°C [221°F]
2) When the port is not under 3-minute restart mode
[Refrigerant recovery (during cooling only, cooling main, heating only, or heating main operation)]
1) When the port is under any condition other than heating Thermo-ON
SV C at the branch is turned on for 30 seconds. ( indicates each port No.)
2) The opening of LEV1 and LEV3 is increased.
Opening of LEV during refrigerant recovery
(Opening of indoor unit LEV: 400 pulses)
Initial opening of LEV
Start
Finish
30 seconds
Содержание PUHY-P168
Страница 11: ... 2 ...
Страница 23: ... 14 ...
Страница 25: ... 16 ...
Страница 38: ... 29 II Restrictions ...
Страница 42: ... 33 II Restrictions ...
Страница 46: ... 37 II Restrictions ...
Страница 50: ... 41 II Restrictions ...
Страница 54: ... 45 II Restrictions ...
Страница 58: ... 49 II Restrictions ...
Страница 75: ... 66 ...
Страница 99: ... 90 III Outdoor Unit BC Controller Components 2 RELAY BOARD RELAY 4 board 3 RELAY BOARD RELAY 10 board ...
Страница 101: ... 92 ...
Страница 111: ... 102 ...
Страница 113: ... 104 ...
Страница 126: ... 117 VI Refrigerant Circuit 1 Refrigerant Circuit Figure 119 2 Principal Parts and Functions 126 ...
Страница 127: ... 118 ...
Страница 134: ... 125 VI Refrigerant Circuit 3 CMB P104 and P108NU GB sub TH25 TH22 LEV3a CP Solenoid valves Block Check valves Block ...
Страница 145: ... 136 ...
Страница 147: ... 138 ...
Страница 185: ... 176 ...
Страница 187: ... 178 ...
Страница 241: ... 232 ...
Страница 243: ... 234 ...
Страница 366: ... 357 IX Troubleshooting ...
Страница 367: ... 358 ...
Страница 368: ... 359 X LED monitor display on the outdoor unit board 1 How to read the LED on the service monitor 361 ...
Страница 369: ... 360 ...