MIV V5 Heat Recovery DC Inverter R410A
DM14-01.01.18en
135
MS Unit Installation
3.4 Hanging the MS
1. Adjust the nut’s site, the interval between gasket (Down Side) and the ceiling should according to actual
construction.
2. Hang the nut of hanging screw bolt into the slotted hole of the installing ear.
3. Use the level gauge to confirm the horizontality of the unit. (Prohibitfalling toward non-drainage side,
better to fall a little toward the drainage side)
4. Drain pipe installation
4.1 Install the drain pipe
1. Please use the flexible drainage pipe to connect the MS drainage port and the PVC pipes, and use the
snap ring for fastening.
2. While connecting other drain pipes please use hard PVC binder and check whether leak or not.
3. The waterspout joints and drain pipes (especially the indoor parts) of the main unit have to wrap up evenly
by insulated casing pipes, and tighten up with lacing belt, in order to prevent air admission and cause
condensation.
4. For avoiding to the condensate water reflow to the air-conditioner inner, the drain pipes should incline
toward the outdoor side (drainage side), the gradient should be over 1/100, and do not turn up defect as
prominence and water absorb etc.
5. While connecting the drain pipes, do not pull so hard for avoiding the main unit effect by force. The
transverse pull-out of the drain pipes should be within 20m, meanwhile, set a supporting point every
0.8~1.0m, for avoiding the flexure of drain pipes; use hard polyethylene (PE)PE pipes to connect the drain
pipes and the connecting pipes, and use the connecting pipes to fasten the drain pipes.
Hanging Bolt
Installing lug
Gasket(Up Side)
Nut(Up Side)
Nut(Down Side)
Gasket(Down Side)
Down Side of the ceiling
Level gauge
Be sure to fasten it!
Snap
ring
Water container
Flexible drainage
pipe
Outlet
PVC water
pipe
(
Φ
1inch(
Φ
25mm)
Hard PVC binder