MIV V5 Heat Recovery DC Inverter R410A
MS Unit Installation
134
3. Body installation
3.1 Install the
Φ
10mm hoisting screw
1. Please
use
Φ
10mm hoisting screw.
2. Remove the ceiling: For different architectural structure, details please contact with indoor decoration
personnel.
Ceiling: For make sure the ceiling level and for avoiding to the ceiling vibration, it must be strengthened
the ceilingplate base frame.
Do not cut off the ceiling plate base frame.
Strengthen the base frame on the both sides of the fixed ceiling.
After hoisting install the main body, it should do the piping and wiring work in the ceiling, decide the outlet
directionsof the pipes after selected the installation location. Especially for the position already has ceiling,
please install pipe, drainage pipe, indoor and outdoor units connecting wires and wire controlling wire to
the connecting positionsbefore hoisting the unit.
3.2 Install the MS
1. Please use the pulley to hoisting install the MS unit on the hoisting bolt.
2. Please use the gradienter to adjust the MS to be horizontal, if not, it may cause water leakage.
3.3 Install the hanging screw bolts
Put rectangular sticks across
the beams, and set pendant
bolts.
Wooden span
Beam
Ceiling
Pendant bolt
Wooden structure
Old concrete roughcast
Use embedded bolts and embedded pulling plugs.
Set and use supportive angle steel.
Steel beam and girder structure
Suspended bolt
Pendant bolt
Supportive angle steel
Set it with embedded bushes or embedded bolts.
New concrete roughcast
Flap type inser
Slide type inser
Concrete iron
Embedded bolt
(With embedded
bolt in pipe)