Settings
196
Pos: 34.25 /BA/Einstellungen/Großpackenpresse/Bindegarn einfädeln/Alte AusführungenBindegarn (Oberfaden) einfädeln Doppelknoter Text @ 21\mod_1239085355805_78.docx @ 228375 @ @ 1
11.1.3.2
Upper twine
Fig. 135
Lead the upper thread (2) coming through the upper twine eyes (1) of the twine box over the
twine guide (3) through the eyes (4) into the upper twine brake (5). From there, lead the upper
twine over the eye of the tensioning arm (6), through the rolls of the upper needle (7) below the
rear cross beam of the knotter table and fasten it onto frame at a suitable point (this could for
example be the hinge pin of the upper tension flap).
Note
Attach the upper twine in a way that there is tension on the tension arm (6).
Note
If the bale compressor is empty, the upper and lower twine strands can be knotted with each
other in the middle of the bale chamber (make sure, that the tension arm (6) is tensioned).
In case the bale channel chamber is filled, it is also possible to lop the loose end of the upper
twine for about 50 cm into the bale channel chamber.
For subsequent baling, the twine is jammed in the forage, thereby pulling the tension arm (6)
downward.
Note
When manually triggering the tying process, make sure that there is tension on the tension arm
(6).