background image

Page 12 

ENGLISH

  

 

Jandy

®

 Pro Series, Hi-E2

®

 and Hi-E2R Gas-Fired Heater   

|

   Installation & Operation Manual

Figure 14.  Field wiring connections.

ATTACH GROUND-

ING WIRE TO 

GREEN GROUND-

ING SCREW

(115 VAC ONLY)

Table 4. 

Gas Supply Pressure Requirements.

Supply Pressure

Minimum

Maximum

Natural Gas

5 inches WC

(125 mm WC)

10.5 inches WC

(265 mm WC)

LP Gas

11 inches WC

(280 mm WC)

14 inches WC

(350 mm WC)

Gas piping must be large enough to provide the required 

gas flow rate without excessive pressure drop. Table 5 

specifies pipe sizes which will limit pressure drop to 0.5 

inches WC (125 Pa), based on the National Fuel Gas 

Code, ANSI Z223.1/NFPA-54.
Do not use flexible appliance connectors on any gas 

connections unless the connector is CSA approved for 

outdoor installation and is marked with the BTUH capacity 

(which must be equal to or greater than the heater rated 

input) and the type of gas (Natural or LP). Also, any 

flexible connectors, such as CSST buried underground 

must be certified for underground installation and meet all 

applicable codes. Please note, use of flexible connector still 

requires the installation of a sediment trap per NFPA 54.

Table 5. 

Required Gas Pipe Size.

Model

Natural Gas

LP Gas

0-50' 

(0-15 m)

50-100' 

(15-30 m)

100-200' 

(30-60 m)

0-80' 

(0-15 m)

50-100' 

(15-30 m)

100-200' 

(30-60 m)

350

1-1/4" 1-1/4" 1-1/2" 1"

1-1/4" 1-1/4"

Support gas piping properly so its weight does not bear on 

the heater. Install a drip leg, a non-restrictive shutoff valve 

and a union on the gas supply line outside of the heater. 

See Figure 13.
Before operating the heater, test the gas supply system, 

including all connections, for leaks using a soap solution. 

Do not use a flame or any ignition source for leak 

detection. Disconnect the heater and its individual gas 

shutoff valve during pressure testing if the test pressure is 

higher than 1/2 psig (3.34 kPa). If the pressure is 1/2 psig 

(3.45 kPa) or lower, close the manual valve on the heater 

gas control during testing.

When the heater is started, check the supply pressure 

to verify that it is adequate during heater operation. 

Undersize piping, a restrictive fitting or an undersize gas 

meter can cause low operating pressure.

High Elevation

To assure good combustion and general operation, gas 

appliances may require manual de-rating when installed 

at high elevation. This is 

not necessary

 with the Hi-E

2

 

because it has a special venturi-type combustion system 

which self-compensates for changes in barometric 

pressure. Air flow through the venturi pulls the correct 

flow of gas into the burner regardless of air density. 

Good quality combustion and high efficiency are assured 

without special adjustment or changes to the heater.

2.9.1  Special Precautions for LP Gas

LP Gas is heavier than air and can therefore more readily 

collect or “pool” in enclosed areas if provision for proper 

ventilation is not made. Installation of pool heaters in 

enclosed areas such as pits is not recommended. However, 

if such an installation is required be sure to pay special 

attention to proper ventilation requirements for LP gas. 

Locate heaters a safe distance from LP gas cylinders and 

filling equipment. Consult the National Fuel Gas Code 

(NFPA 54 / ANSI Z223.1, latest edition), the Natural 

Gas and Propane Installation Code in Canada (CAN/

CSA B149.1, latest edition), and any other local codes 

and fire protection authorities about specific installation 

restrictions in your area.

2.10  Electric Wiring

 WARNING

ELECTRICAL SHOCK HAZARD.

 This heater contains 

wiring that carries high voltage. Contact with these 

wires may result in severe injury or death.

CAUTION

Label all wires prior to disconnection when servicing 

controls. Wiring errors can cause improper and dangerous 

operation. Verify proper operation after servicing.

2.10.1. Electrical Power

Electrical wiring must be in accordance with the latest 

edition of the National Electrical Code® (NEC®), ANSI/

National Fire Protection Association® (NFPA) 70, unless 

local code requirements indicate otherwise; and in Canada 

with latest edition of CSA C22.1 Canadian Electrical 

Code.

Содержание HI-E2

Страница 1: ...ion and or operation can create carbon monoxide gas and flue gases which can cause serious injury property damage or death For indoor installations as an additional measure of safety Zodiac Pool Syste...

Страница 2: ......

Страница 3: ...tion 17 2 12 2 Start up 17 2 12 3 Condensate 17 2 12 4 Gas Pressure 18 2 12 5 Adjustment of Water Pressure Switch 18 2 12 6 Water Temperature Rise 19 Section 3 Operating Instructions 19 3 1 Start Up P...

Страница 4: ...arranty The Hi E2 is sold with a limited factory warranty A copy of the warranty is included in a plastic bag inside the heater The warranty does not cover damage caused by improper installation opera...

Страница 5: ...building codes for additional requirements CAUTION When pool equipment is located below the pool surface a leak from any component can cause large scale water loss or flooding Zodiac Pool Systems Inc...

Страница 6: ...of the heater The correct size drill bit is usually provided with the concrete screws when purchased Place a screw in each of the holes and fasten the heater to the equipment pad see Figure 2 Do not o...

Страница 7: ...and Ventilation Air Model Required net free area in square inches sq cm for each of 2 openings one 1 near ceiling and one 1 near floor Directly Through an Exterior Wall Through Horizontal Ducts 350 88...

Страница 8: ...boratory NRTL as being compliant with the applicable requirements of the Underwriters Laboratories UL standard for safety for Venting Systems for Gas Burning Appliances Categories II III and IV ANSI U...

Страница 9: ...on inlets etc In the United States this distance must be at least 4 feet 1 21 m In Canada it must be at least 10 feet 3 04 m five 5 elbows Per Table 3 Only 16 feet of 4 vent pipe would be allowable wh...

Страница 10: ...e it can be disposed of properly Support vent piping with suitable hangers so its weight does not bear on the heater or building penetration and so that piping joints are not strained Support horizont...

Страница 11: ...wer A package of limestone gravel neutralizer is provided with the condensate assembly Remove the neutralizer from the packing and spread evenly throughout the tray and around the properly placed tube...

Страница 12: ...s control during testing When the heater is started check the supply pressure to verify that it is adequate during heater operation Undersize piping a restrictive fitting or an undersize gas meter can...

Страница 13: ...aune Vert Mauve GY Gray Gris COMB FAN Ventilateur combustion 115V 60Hz H0205500F IGN120 IND W W BK GY R BR TR TH DIGITAL IGNITION CONTROL BK Hi E2 Figure 15 Wiring diagram Hi E2 pool heater The Hi E2...

Страница 14: ...ff from a remote location Contact your local Jandy Pro Series distributor for information on the AquaLink RS control system to fit your back yard recreational needs An interrupt on off type remote can...

Страница 15: ...the brass fitting 5 Remove the temperature control sensor by removing the retainer bracket and its cap screws 6 Disconnect the limit switch wires from the limit switches The limit switches and the sho...

Страница 16: ...d A pressure relief valve is not supplied with the Hi E2 All equipment installations need to be in accordance with the manufacturers instructions To install a pressure relief valve 1 Remove the 3 4 br...

Страница 17: ...in the system when installing a PRV Any pressure relief valve installed must comply with provisions of the standard described in ANSI Z21 22 for the United Sates or CSA 4 4 in Canada Some local codes...

Страница 18: ...its operation and settings as outlined in the maintenance section of this manual 2 12 4 1 Step down Gas Pressure Regulator The step down regulator does not change requirements for gas supply piping o...

Страница 19: ...tem or a larger pump Before proceeding with either remedy verify proper heater operation Low gas input results in low temperature rise and vice versa A problem with the heater internal bypass assembly...

Страница 20: ...de of the service door and also on the inside of the control compartment door Lighting instructions are as follows 1 Turn off all electrical power to the heater at the main junction box 2 Open the con...

Страница 21: ...factor of the pool water between 7 4 and 7 6 See Table 7 for guidelines on other chemical measurements 3 4 2 Spas The proper chemical balance in spa water is more critical than in a swimming pool hea...

Страница 22: ...se spas or hot tubs 3 4 2 2 Saturation Index PH Total Alkalinity TA temperature Calcium Hardness and Total Dissolved Solids TDS play a role in whether the water is either corrosive or scale forming Th...

Страница 23: ...the 78 F 26 C level before expected usage keeping in mind to allow enough lead time for the water to reach the desired temperature 6 During the winter shut down the heater by following the lighting a...

Страница 24: ...technician when inspecting and servicing the heater To reactivate the heater in the spring have a qualified professional technician reassemble the heater as follows 1 Attach the pressure switch fitti...

Страница 25: ...lter and strainers aren t clogged that there are no mis positioned water valves that the gas or electric power supplies aren t shut off and that time clocks are properly adjusted Also be sure that the...

Страница 26: ...ixture monitors the flame and controls the combustion blower and gas valve When the temperature control requires heat the ignition control starts the blower providing a pre purge of the combustion cha...

Страница 27: ...tings or similar devices may be the problem Voltage outside of the above range may be due to poor wiring poor connections other loads such as air conditioning compressors or to an electric utility com...

Страница 28: ...ectrical power or setting the control to Off 4 5 2 3 Fireman Switch and External Interlocks Probe for voltage at point 3 the other connection of the terminal block which has a white wire connected to...

Страница 29: ...l for heat Observe that the normal sequence takes place by noting blower operation the glow of the igniter through the combustion chamber sight glass and then voltage at point 8 If the blower does not...

Страница 30: ...on heater The manometer will read zero until the gas valve opens and then it will indicate the gas orifice differential The gas orifice differential should be 4 0 0 3 WC for a unit at sea level See s...

Страница 31: ...other elevations Note that when the heater is operated with the gas valve off it will eventually lock out because the ignition control does not sense flame Normally there will be enough time to obtai...

Страница 32: ...ockage in the combustion air supply system Correct any such problems and verify normal operation by returning to the venturi system checkout procedures Pressure readings will be less if the heater is...

Страница 33: ...eration Check for blockage by disconnecting drainage tubes at the collector and the vent diffuser Probe these openings with a tool or wire hook to dislodge any debris Limestone gravel neutralizer is r...

Страница 34: ...04300 18 By Pass Valve Assembly 350 R0304400 19 Flow Control Cap 350 S0076700 20 By Pass Valve Gasket 350 R0011400 21 By Pass Valve Spring 350 R0304500 22 By Pass Valve Rod 350 R0304900 23 By Pass Val...

Страница 35: ...oor Exhaust Grill 350 R0348400 57 Indoor Vent Collar not shown 350 R0307900 58 Condensate Trap Assembly 350 R0303300 59 Limestone Gravel 350 R0306200 60 Condensate Trap Cover 350 R0213300 Venturi Hard...

Страница 36: ...ired Heater Installation Operation Manual 42 46 65 66 12 45 44 43 55 56 86 40 30 38 41 83 84 30A 34 32 33 39 36 37 35 6 4 10 1316 48 85 54 1 75 81 87 53 50 51 52 17 14 3 18 23 15 29 49 8 9 2 5 58 60 6...

Страница 37: ...Page 37 ENGLISH Jandy Pro Series Hi E2 and Hi E2R Gas Fired Heater Installation Operation Manual NOTES...

Страница 38: ...Page 38 ENGLISH Jandy Pro Series Hi E2 and Hi E2R Gas Fired Heater Installation Operation Manual NOTES...

Страница 39: ...Page 39 ENGLISH Jandy Pro Series Hi E2 and Hi E2R Gas Fired Heater Installation Operation Manual NOTES...

Страница 40: ...CA 92081 1 800 822 7933 www jandy com ZODIAC is a registered trademark of Zodiac International S A S U used under license All other trademarks referenced herein are the property of their respective ow...

Отзывы: