Guideline
Explanation/comment
Do not install and operate the equipment in closed
systems unless the system is constructed with
properly-sized safety devices and control devices.
Acceptable devices:
•
Pressure relief valves
•
Compression tanks
•
Pressure controls
•
Temperature controls
•
Flow controls
If the system does not include these devices, consult the engi-
neer or architect in charge before you operate the pump.
Take into consideration the occurrence of unwant-
ed noise and vibration.
The best pump location for noise and vibration absorption is on
a concrete floor with subsoil underneath.
If the pump location is overhead, undertake special
precautions to reduce possible noise transmission.
Consider a consultation with a noise specialist.
5.1.2 Foundation requirements
Requirements
•
The location and size of the foundation bolt holes must match those shown on the assembly draw-
ing provided with the pump data package.
•
The foundation must weigh between two and three times the weight of the pump.
•
Provide a flat, substantial concrete foundation in order to prevent strain and distortion when you
tighten the foundation bolts.
•
The concrete foundation must have sufficient firmness according to DIN 1045 or equal standard.
Sleeve-type bolts
1
2
3
4
5
6
Item Description
1.
Baseplate
2.
Shims
3.
Foundation
4.
Sleeve
5.
Dam
6.
Bolt
Figure 4: Sleeve type bolts
5.1 Pre-installation
ICB Installation, Operation and Maintenance Instruction