1.
Baseplate
2.
Shims
3.
Form
4.
Concrete
5.
Anchor bolt
6.
Bolt sleeve
7.
Grout
Figure 16: Baseplate grouting
1.
Build a strong form around the foundation to contain the grout.
2.
Soak the top of the foundation thoroughly, then remove surface water.
3.
Completely fill the baseplate with grout.
If necessary, temporarily use air relief tubing or drill vent holes in order to remove trapped air.
4.
After the grout has completely hardened, tighten the foundation bolts.
It will take approximately 24 hours for the grout to harden.
5.
Check the alignment.
6.
Approximately fourteen days after the grout has been poured and the grout has completely dried,
apply an oil-based paint to the exposed edges of the grout in order to prevent air and moisture from
coming in contact with the grout.
4.5 Piping checklists
4.5.1 General piping checklist
Precautions
WARNING:
•
Risk of premature failure. Casing deformation can result in misalignment and contact with
rotating parts, causing excess heat generation and sparks. Flange loads from the piping
system, including those from the thermal expansion of the piping, must not exceed the
limits of the pump.
•
Risk of serious personal injury or property damage. Fasteners such as bolts and nuts are
critical to the safe and reliable operation of the product. Ensure appropriate use of fasten-
ers during installation or reassembly of the unit.
•
Use fasteners of the proper size and material only.
•
Replace all corroded fasteners.
4.5 Piping checklists
32
Model 3410 Installation, Operation, and Maintenance Manual
Содержание GOULDS PUMPS 3410
Страница 1: ...Installation Operation and Maintenance Manual Model 3410 ...
Страница 2: ......