Confidential Information - Do Not Distribute
Fig. 51 – Lifting the Acquisition Unit with the forklift
2.
Look at the base of the Acquisition Unit: there are four holes at the
corners: Align these holes with the four holes drilled on the slip
aluminium sheet of the Trailer;
Fig. 52 – Drilled holes on the Trailer for Acquisition Unit installation
3.
fasten the screws (M12 x 50 mm hexagonal head) through the holes
in order to fix the Acquisition Unit base to the trailer (two 19 mm
wrenches are needed). Check the fastening of the self-blocking nut in
order to ensure the perfect immobility of the Acquisition Unit;
Fig. 53 – Fix the Acquisition Unit base to the trailer
4.
remove the wings frame from the Acquisition Unit (
). A 14 mm
Allen Key and a 27 mm wrench are required to unfasten the four
screws with related nuts (
Fig. 54 – Removing wings from installed Acquisition Unit