IDS1000-A Air-Cooled Container Data Center
All-in-One Maintenance Guide
5 Parts Replacement
Issue 01 (2016-01-10)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
108
Documents required: collector port layout diagram, documents delivered with the ECC500
collector, initial configuration parameters for the management system
Skill requirement: weak-current engineer
For the diagram and table, see the initial configuration guide.
Procedure
Step 1
Remove all cables and mark the cables clearly.
Step 2
Remove the four captive screws from the ECC500 collector using a Phillips screwdriver, as
shown in
Figure 5-26
Removing the faulty ECC500 collector
Step 3
Install a new collector, and tighten the screws in reverse order of
Step 4
Reconnect all cables based on the cable labels.
Step 5
Start the ECC500 collector and check that the new collector is working properly.
If the power indicator on the main control module of the ECC500 collector is on and the ECC500
collector is communicating properly with the management system, the ECC500 collector is working
properly.
Step 6
Configure the ECC500 collector and ports based on the management system initial
configuration table for the solution in use.
----End