4.
In the Verifying Jobs Options dialog box (
Figure 105
), specify the job attributes as follows:
1.
Under Scheduling Type, select one of the following:
• Click
Start Now
to start the job immediately.
• Click
Schedule for Later
, and then enter a Start Time and Start Date.
• Click
Serial Schedule Jobs
, and then assign a priority (1–256) in the Job Priority box,
where a lower value indicates that the job is scheduled earlier than jobs configured with
higher values. For details on Serial Schedule Jobs, see “
Starting serial scheduled
jobs
” on page 163.
2.
In the Group Name box, select a job group name from the list. The group name makes it
easier to view the job status on a group basis.
3.
In the
IO Size
box, either select one of the default I/O sizes, or enter a custom value.
Figure 105 Verifying jobs options
.
4.
To save the verifying jobs options, click
Apply
or, to abandon changes to this job verification,
click
Cancel
.
5.
Add the source and destination LUN. For details, see “
Using the Data Migration
Wizard
” on page 155.
Acknowledging a data migration job
The mpx Manager keeps track of all data migration jobs until you either delete them from the system
or acknowledge them after job completion. You must acknowledge jobs to free up the destination
LUN so that it can become part of another job, if required.
To acknowledge a completed data migration job:
1.
In the left pane of the mpx Manager, select the
Services
tab, and then click
Data Migration Jobs
.
2.
In the right pane, select the
Completed Data Migration Jobs
tab to bring that page to the front.
Offline Data Migration
180
Содержание Storageworks 8100 - enterprise virtual array
Страница 20: ...20 ...
Страница 30: ...MPX200 Multifunction Router overview 30 ...
Страница 47: ...Figure 27 iSCSI controller options Remove controller MPX200 Multifunction Router 47 ...
Страница 48: ...Managing the MPX200 using HP Command View EVA 48 ...
Страница 59: ...Figure 32 Virtual disk properties Figure 33 Host details MPX200 Multifunction Router 59 ...
Страница 112: ...MPX200 iSCSI configuration rules and guidelines 112 ...
Страница 219: ...Load Balancing Enabled Array License Not Applied MPX200 Multifunction Router 219 ...
Страница 222: ...Controller Id WWPN PortId Path Status 0 20 78 00 c0 ff d5 92 e5 02 04 00 Current Optimized Offline Data Migration 222 ...
Страница 248: ...Offline Data Migration 248 ...
Страница 258: ...Diagnostics and troubleshooting 258 ...
Страница 306: ...Command referencecommand reference 306 ...
Страница 330: ... Blade number 1 or 2 Simple Network Management Protocol setup 330 ...
Страница 368: ...Saving and restoring the MPX200 configuration 368 ...
Страница 402: ...Data migration best practices 402 ...
Страница 408: ...408 ...