6. Route the cable for the water pressure sensor (6,
Fig. 09) down out of the control and connect to the
boiler at the bottom (cable routing acc. to Fig. 09).
Route all other cables on the left or right of the boiler
and make the plug connections.
CAUTION
The cables must not touch any hot parts.
7. Hook the lower rear wall (7, Fig. 09) onto the side
walls. Hook in the rear walls (7a, 7b, Fig. 09) on the
opposite side and engage together on the side walls.
8. Mount the upper side walls (8, 8a, Fig. 09). Place
the underside of the upper side walls (long slot) onto
the special screws of the lower side walls and push
in. Secure the upper side walls using 4 self-trapping
screws (8b, Fig. 09) ø 3.5 x 10.
9.
Hook in the upper rear walls (9, Fig. 09) and fit the
dummy cover (9a).
10. Put on cover plates (10, Fig. 09). Install the upper
front (10a, Fig. 09) and place the pins in slits, then
push back. Following that, secure with carriage bolt
(10b, Fig. 09). (When taking down, lift one side fol-
lowed by the other.)
11. Hook the front cover (11, Fig. 09) in at the bottom
(from type 575 onwards with rail) and push closed
upwards (secure with carriage bolt on the side). In a
cascade > 3, no carriage bolts are fitted on the middle
boilers!
12. The remaining 3 casing walls (12, 12a, 12b, Fig. 11)
are fitted after mounting the condensate box.