GREE GMV5E DC INVERTER VRF UNITS SERVICE MANUAL
108
on the master unit to confirm. The main board is displayed as follows and the unit automatically enters
commissioning step 04.
Commissioning Code
Progress Code
Status Code
Progress
LED1
LED2
LED3
Code
Display Status
Code
Display Status
Code
Display Status
03_Module quantity
confirmation
db
On
03
On
OC
On
If the displayed quantity is inconsistent with the number of actually connected modules, check
whether communication cables are correctly connected between modules in power-off status. Then
perform commissioning again.
Note:
It is very important to correctly confirm the number of ODUs. If the confirmed quantity is
inconsistent with the actual quantity, the system may improperly run.
Step 9: When the unit runs to step 04, users need to manually confirm the number of indoor
modules. The main board of each module is displayed as follows:
Commissioning Code
Progress Code
Status Code
Progress
LED1
LED2
LED3
Code
Display Status
Code
Display Status
Code
Display Status
04_Indoor unit quantity
confirmation
db
On
04
On
Number of
connected IDUs
Blinking
If the displayed quantity is consistent with the number of actually connected modules, press "SW7"
on the master unit to confirm. The main board is displayed as follows and the unit automatically enters
the next commissioning step.
Commissioning Code
Progress Code
Status Code
Progress
LED1
LED2
LED3
Code
Display Status
Code
Display Status
Code
Display Status
04_Indoor unit quantity
confirmation
db
On
04
On
OC
On
Note:
It is very important to correctly confirm the number of IDUs. If the confirmed quantity is
inconsistent with the actual quantity, the system may improperly run.
Step 10: Unit commissioning step 05 is internal communication detection.
If no exception is detected, the main board is displayed as follows and the unit automatically enters
the next commissioning step.
Commissioning Code
Progress Code
Status Code
Meaning
Progress
LED1
LED2
LED3
Code
Display Status
Code
Display Status Code
Display Status
05_Internal
communication
detection
db
On
05
On
OC
On
The system completes
detection and automatically
enters the next step.
Содержание /E-X
Страница 27: ...GREE GMV5E DC INVERTER VRF UNITS SERVICE MANUAL 23 Any nonconformity must be resolved through coordination...
Страница 233: ...GREE GMV5E DC INVERTER VRF UNITS SERVICE MANUAL 229 Troubleshooting...
Страница 239: ...GREE GMV5E DC INVERTER VRF UNITS SERVICE MANUAL 235 Troubleshooting...
Страница 308: ...JF00303085...