6 FUNCTIONAL TESTS (USER SETTINGS)
6.2 MEASURING UNIT TESTS
6
3.
Set the relay into test mode 27 (Phase Overcurrent). The LUI should display
INST PHS OVRC ON
4.
Set
I
op
to 0.55 x 50PICKUP = [________] A rms and apply to the relay. The A1 contact should close.
Lower
I
op
to 0.45 x 50PICKUP = [________] A rms, at which point the A1 contact should open.
5.
Reduce
I
op
to 0 A.
6.2.7 T7 – GROUND INSTANTANEOUS OVERCURRENT TEST
1.
Protection settings:
OVERCURRNT
(605)
50G = YES
(606)
50G_DIRCNL = NO
(607)
50GPICKUP = [________] Amps
(610)
51G = NO
LINEPICKUP
(801)
LINEPICKUP = NO
The 50G function is given by:
50G = 3
I
0
+ 0.9
I
1
(eq. 6–1)
where
I
0
is the zero-sequence current and
I
1
is the positive-sequence current. Since the test current
I
op
is
single phase,
I
0
and
I
1
are given by:
Substituting Equations 6–2 and 6–3 into Equation 6–1 yields:
50G =
I
op
– 0.3
I
op
= 0.7
I
op
(eq. 6–4)
Therefore,
I
PT
will pick up when:
2.
Connect the relay as shown in Figure 4–3: PHASE TO GROUND TEST CONNECTIONS on page 4–16.
3.
Set the relay into test mode 28 (Ground Overcurrent). The LUI displays
INST GND OVRC ON
4.
Set
I
op
to (50GPICKUP / 0.7) + 0.5 = [________] A rms and apply to the relay. The A1 contact should
close. Lower
I
op
to (50GPICKUP / 0.7) – 0.5 = [________] A rms, at which point the A1 contact should
open.
5.
Reduce
I
op
to 0 A.
I
0
I
op
3
-------
=
(eq. 6–2) and
I
1
I
op
3
-------
(eq. 6–3)
=
I
PT
50GPICKUP
0.7
---------------------------------
≥
Содержание LPS-O
Страница 2: ......
Страница 4: ......
Страница 14: ...x LPS O Line Protection System GE Power Management TABLE OF CONTENTS ...
Страница 40: ...1 26 LPS O Line Protection System GE Power Management 1 10 ELEMENTARY DIAGRAM 1 PRODUCT DESCRIPTION 1 ...
Страница 112: ...3 16 LPS O Line Protection System GE Power Management 3 3 PRINTED CIRCUIT BOARD MODULES 3 HARDWARE DESCRIPTION 3 ...
Страница 166: ...6 16 LPS O Line Protection System GE Power Management 6 4 BACKUP PROTECTION TESTS 6 FUNCTIONAL TESTS USER SETTINGS 6 ...
Страница 200: ...8 32 LPS O Line Protection System GE Power Management 8 4 REMOTE COMMUNICATION INTERFACE 8 LOCAL USER INTERFACE 8 ...
Страница 208: ...9 8 LPS O Line Protection System GE Power Management 9 3 TROUBLESHOOTING 9 SERVICING 9 ...
Страница 226: ...10 18 LPS O Line Protection System GE Power Management 10 8 HELP MENU 10 ALPS TEST PROGRAM 10 ...
Страница 280: ...13 18 LPS O Line Protection System GE Power Management 13 4 CREATING XPRESSION BUILDER LOGIC 13 XPRESSION BUILDER 13 ...
Страница 284: ...A 4 LPS O Line Protection System GE Power Management A 1 FREQUENTLY ASKED QUESTIONS APPENDIXA A ...
Страница 288: ...B 4 LPS O Line Protection System GE Power Management B 2 FIGURES APPENDIXB B ...
Страница 292: ...C 4 LPS O Line Protection System GE Power Management C 1 KEYPAD MENUS APPENDIXC C ...
Страница 294: ...D 2 LPS O Line Protection System GE Power Management D 1 WARRANTY INFORMATION APPENDIXD D ...
Страница 306: ...xii LPS O Line Protection System GE Power Management INDEX INDEX ...
Страница 307: ...GE Power Management LPS O Line Protection System NOTES ...