LPS-O Line Protection System
GE Power Management
5.3 PHASE-TO-PHASE ZONE REACH TESTING
5 FUNCTIONAL TESTS (FACTORY SETTINGS)
5
5.3 PHASE-TO-PHASE ZONE REACH TESTING
5.3.1 T11 – ZONE 1 PHASE REACH TEST
1.
Protection Settings:
Z1DISTANCE
(101)
Z1PHASE = YES
(104)
Z1P_TIME = 0.0 sec.
Z2DISTANCE
(201)
Z2PHASE = NO
Z3DISTANCE
(301)
Z3PHASE = NO
Z4DISTANCE
(401)
Z4PHASE = NO
LINEINFO
(1204) TRSMFRTYPE = NONE
2.
Connect the relay as shown in Figure 5–1: PHASE-TO-PHASE TEST CONNECTIONS on page 5–7 for
the appropriate phases under test. Set the relay to test mode 14 (Any Zone 1 Phase). The LUI displays:
ANY Z1 PHASE ON
3.
Set the voltage inputs to the following values:
VA: 67 volts rms
∠
0°,
VB: 67 volts rms
∠
–120°,
VC: 67 volts rms
∠
+120°.
4.
Set the phase angle of the fault current
I
op
to the phase-angle value listed in Table 5–2: FAULT CURRENT
PHASE SETTINGS FOR TEST T11. Note that the leading phase angle is 180° out of phase with the line to
which it is shorted.
5.
Set the fault current to 10.0 (2.0) amps rms. Reduce the voltage of the faulted phases and check that the
A1 contact closes when the voltages are within the limits shown in Table 5–2: FAULT CURRENT PHASE
SETTINGS FOR TEST T11.
6.
Reduce the fault current to zero. Note that the trip target indication concurs with the fault. For example, an
AB fault is displayed as follows:
TRIP AB Z1 “DIST”
Table 5–2: FAULT CURRENT PHASE SETTINGS FOR TEST T11
∠
I Degrees
Volts rms
Displayed Target
†
–25
51 to 57
–
–55
59 to 66
82 to 88
–85
51 to 57
–
†
Reference only
Содержание LPS-O
Страница 2: ......
Страница 4: ......
Страница 14: ...x LPS O Line Protection System GE Power Management TABLE OF CONTENTS ...
Страница 40: ...1 26 LPS O Line Protection System GE Power Management 1 10 ELEMENTARY DIAGRAM 1 PRODUCT DESCRIPTION 1 ...
Страница 112: ...3 16 LPS O Line Protection System GE Power Management 3 3 PRINTED CIRCUIT BOARD MODULES 3 HARDWARE DESCRIPTION 3 ...
Страница 166: ...6 16 LPS O Line Protection System GE Power Management 6 4 BACKUP PROTECTION TESTS 6 FUNCTIONAL TESTS USER SETTINGS 6 ...
Страница 200: ...8 32 LPS O Line Protection System GE Power Management 8 4 REMOTE COMMUNICATION INTERFACE 8 LOCAL USER INTERFACE 8 ...
Страница 208: ...9 8 LPS O Line Protection System GE Power Management 9 3 TROUBLESHOOTING 9 SERVICING 9 ...
Страница 226: ...10 18 LPS O Line Protection System GE Power Management 10 8 HELP MENU 10 ALPS TEST PROGRAM 10 ...
Страница 280: ...13 18 LPS O Line Protection System GE Power Management 13 4 CREATING XPRESSION BUILDER LOGIC 13 XPRESSION BUILDER 13 ...
Страница 284: ...A 4 LPS O Line Protection System GE Power Management A 1 FREQUENTLY ASKED QUESTIONS APPENDIXA A ...
Страница 288: ...B 4 LPS O Line Protection System GE Power Management B 2 FIGURES APPENDIXB B ...
Страница 292: ...C 4 LPS O Line Protection System GE Power Management C 1 KEYPAD MENUS APPENDIXC C ...
Страница 294: ...D 2 LPS O Line Protection System GE Power Management D 1 WARRANTY INFORMATION APPENDIXD D ...
Страница 306: ...xii LPS O Line Protection System GE Power Management INDEX INDEX ...
Страница 307: ...GE Power Management LPS O Line Protection System NOTES ...