13-9-666 Page 45
REMOTE MOUNTED ELEVATED COOLER ASSEMBLY PROCEDURE
- The Compressor package will
be built and tested with the coolers mounted on the package. On enclosed units, the fan motor will be
disconnected after test and the vent fan motor connected in its place. The vent fan will be mounted in the
enclosure. A contactor (starter) will be shipped loose and remote mounted with the cooler by others upon
start-up at the job site. The control box will be wired for remote elevated coolers at the factory.
NOTICE
All requirements of local codes should be followed.
When connecting pipe fittings to the cooler, support the threaded coupling with a pipe wrench when
tightening the connection. Use silicone sealant on all steel to aluminum threaded connections. All piping
should be firmly supported to avoid strain on the cooler manifold and connections. Flexible connections
should be installed in all interconnecting piping, adjacent to the cooler, to avoid transmitting piping weight
or vibrations to the cooler elements. Before beginning installations, check to be sure that no debris or
foreign matter remains in the couplings or cooler bodies. Be certain interconnecting piping is clean to
avoid clogging the cooler passages.
Figure 5-5 – COOLER DRAIN DETAIL
AFTERCOOLER PIPING
- At shutdown of the system, all units should be drained completely of
condensate if there is any possibility of freezing or corrosion damage. To help remove the condensate,
the cooler may be tapped per Figure 5-5, page 45, and a drain cock installed. After opening the drain
cock, blow air into the cooler from a connection on the opposite side of the cooler. At the same time the
connection on the drain side of the cooler should be plugged. The drain cock should be left open until the
machines are ready for start-up.
WARNING
Failure to remove condensate from an idle cooler in freezing temperatures will
cause permanent cooler damage. Drain condensate after system shutdown. It
is the owner/operator's responsibility to ensure that condensate has been
drained and cooler dried out to prevent cooler damage.
Содержание ELECTRA-SAVER EAQ99Q
Страница 10: ...13 9 666 Page 3 Figure 1 4 COMPRESSOR MOTOR SIDE Figure 1 5 COOLER RESERVOIR SIDE 200EDM797 A Ref Drawing...
Страница 11: ...13 9 666 Page 4 Figure 1 6 AIR OIL FLOW DIAGRAM 202EDM797 Ref Drawing...
Страница 13: ...13 9 666 Page 6 DECALS 206EAQ077 212EAQ077 218EAQ077 211EAQ077 207EAQ077...
Страница 14: ...13 9 666 Page 7 DECALS 216EAQ077 217EAQ077 222EAQ077 221EAQ077 208EAQ077...
Страница 43: ...13 9 666 Page 36 Figure 4 13 WIRING DIAGRAM WYE DELTA EBQ EBU UNITS 300EDM546 A Ref Drawing...
Страница 44: ...13 9 666 Page 37 Figure 4 14 WIRING DIAGRAM FULL VOLTAGE EBQ EBU UNITS...
Страница 45: ...13 9 666 Page 38 Figure 4 15 WIRING DIAGRAM WYE DELTA EAQ EAU UNITS ONLY 301EAQ546 B Ref Drawing...
Страница 46: ...13 9 666 Page 39 Figure 4 16 WIRING DIAGRAM FULL VOLTAGE EAQ EAU UNITS ONLY 303EAQ546 Ref Drawing...
Страница 50: ...13 9 666 Page 43 Figure 5 3 FLOW DIAGRAM AIR OIL SYSTEM 203EDM797 A Ref Drawing...