63
Revision date: 12.02.16
Inflation Fan Kit Installation
Once the air inflation kit or kits are installed, install the remaining layer of
film for the greenhouse (#108661). Simply repeat the steps for the cover
installation for your greenhouse.
Follow these guidelines to install the remaining film:
Ensure that the deflector bushing for the air inflation kit remains in
place when the final film is pulled.
Secure film in all the same channels as the first film--111614Z144
along the ridge vent, 104546 along the end rafters, and 11614Z144
along the side walls.
Add a second run of 102198 spring wire over the first.
Be careful not to damage the first film during the installation and
cutting of the second film.
Test the air inflation system after installing the second film.
Photo shows pulling the second layer of film onto the frame. End wall shows optional roll-up door panel. Additional
purchase required. Actual building will differ from what is shown.
Photo shows an installed air
inflation system as seen from
inside a greenhouse.
Содержание Growers Supply GrowSpan 500 Series
Страница 22: ...22 Revision date 12 02 16 Frame Assembly 5 0 66 0 FRQWLQXHG Customer supplied rafter spacing jig ...
Страница 65: ...65 Revision date 12 02 16 Roll Up Side Panel Installation ...
Страница 111: ...111 Revision date 12 02 16 Additional Notes Space below is reserved for customer notes ...