36
④
Check the PV array’s insulation to ground with a multimeter: make sure that the
insulation resistance to ground is greater than 1 MOhm.
Danger to life due to the presence of AC voltage
• Only touch the insulation of the AC cables.
• Wear personal protective equipment such as insulating gloves.
⑤
Check the grid voltage: check that the grid voltage at the point of connection of the
inverter complies with the permitted value.
7.2 Mechanical checks
Carry out the main mechanical checks to ensure the inverter is waterproof:
①
Make sure the inverter has been correctly mounted with wall bracket.
②
Make sure the cover has been correctly mounted.
③
Make sure the communication cable and AC connector have been correctly wired
and tightened.
7.3 Safety code check
Choose suitable safety code according to the location of installation. please visit
website (
http://pro.gsmarte.com
) and download the GSMARTE manual for detailed
information.
Information for safety code
The inverters comply with local safety code when leaving the factory.
7.4 Start-Up
After finishing the electrical and mechanical checks, switch on the miniature
circuit-breaker and DC-switch in turn. Once the DC input voltage is sufficiently high and
the grid-connection conditions are met, the inverter will start operation automatically.