4 Operation
4.1 Checklist for commissioning
Rapid Link 5 · RAMO5 · RASP5
10/19 MN034004EN
www.eaton.com
107
4 Operation
4.1 Checklist for commissioning
Before commissioning Rapid Link Modules RAMO5 and RASP5, check the
following points (checklist):
Number
Activity
Note
1
Mounting and wiring completed in accordance with the applicable instructional leaflets
(
→
IL034084ZU and IL034085ZU).
2
All wiring and line section leftovers, as well as all the tools used, have been removed from the
RAMO5, RASP5, motor’s and drive unit’s proximity.
3
All plug connectors in the power section are made as described in this manual.
→
The AS-i bus must be plugged in and powered in manual mode as well.
4
The cables connected to the RAMO5 and RASP5 Rapid Link Modules are
not
shorted and
not
connected to ground (PE), except PE cable.
5
On speed control unit RASP5 the heat sink is correctly grounded (PE).
6
All electrical connections on the motor are established correctly.
→
On RASP5, metal motor plugs are permissible only with a motor cable length of up to 5 m.
7
Each single phase of the supply voltage (power bus L1, L2, L3) is protected with a fuse.
8
The Rapid Link modules RAMO5, RASP5 and the motor are adapted to the mains voltage.
section 1.3, “Rated operational data on the nameplate”, page 15, connection type (star, delta) of
the motor tested.
9
The quality and volume of cooling air are in line with the environmental conditions required for the
RAMO5, RASP5 and the motor.
10
All connected control cables and switchgear will ensure that the required stop conditions will be met.
11
The parameters that were preset at the factory have been checked with the list of parameters.
12
The effective direction of a coupled machine will allow the motor to start.
13
All emergency stop functions and safety functions are in an appropriate condition.
Содержание Rapid Link RAMO5
Страница 1: ...Manual Rapid Link 5 RAMO5 RASP5 10 19 MN034004EN ...
Страница 4: ...II ...
Страница 10: ...6 Rapid Link 5 RAMO5 RASP5 10 19 MN034004EN www eaton com ...
Страница 122: ...4 Operation 4 3 Manual control 118 Rapid Link 5 RAMO5 RASP5 10 19 MN034004EN www eaton com ...
Страница 136: ...5 RAMO5 Motor starter 5 7 Configure special settings 132 Rapid Link 5 RAMO5 RASP5 10 19 MN034004EN www eaton com ...
Страница 158: ...8 PC tool 8 2 Parameter Editor 154 Rapid Link 5 RAMO5 RASP5 10 19 MN034004EN www eaton com ...
Страница 164: ...9 Control Unit 9 2 Extended parameter set 160 Rapid Link 5 RAMO5 RASP5 10 19 MN034004EN www eaton com ...
Страница 194: ...10 Parameter list 10 4 Parameter groups for RASP 190 Rapid Link 5 RAMO5 RASP5 10 19 MN034004EN www eaton com ...
Страница 208: ...11 Communications 11 5 OP Bus 204 Rapid Link 5 RAMO5 RASP5 10 19 MN034004EN www eaton com ...
Страница 216: ...12 Error messages 12 3 RASP Error list 212 Rapid Link 5 RAMO5 RASP5 10 19 MN034004EN www eaton com ...