Installing the Ergonomic Workstation
Route Cables
Follow these instructions for an overview on how to route cables through the assembled
components to a power source. These instructions are intended to provide general guidelines
only since configurations may vary.
To route cables, do the following:
1. Route the power control cable from the power control switch (96239) through the channel
in the workstation support frame to the control box (90066). When routing cables, adhere
to these guidelines:
a. The DL2 lift is to be connected to the sockets on the control box by means of the
motor cables, which have a 6-pin plug in each end.
b. The mains cable is to be mounted and power switched on. Please note that the
control box must only be connected to the voltage stated on the label.
c.
The control box earth cable should be mounted on the workstation in a way that
ensures good electrical contact. The function of the earth cable is to earth the
desk and ground static electricity. The earth connection does not protect other
electrical products.
2.
Route the power cable from the control box (90066) through the workstation support
frame, cable chain, and lower frame to a power outlet.
See Port
Connections Detail
Refer to the following port connections illustration and perform the following instructions to
connect each cable to the appropriate port.
29
Eaton Profile Genesys Dual-Lift Ergonomic Workstation Installation www.eaton.com/powerquality 11-41 06-2011