Service Manual for Flexible Batch Broiler, CE Version
15
6/19/2014
SM-BR-BR-0007
7. Loosen the two setscrews on motor sprocket
and remove sprocket from motor shaft.
8. Reverse procedure to install a new Conveyor
Drive Motor Sprocket, ensuring that one set
screw is tightened to the flat side of the motor
shaft.
NOTE:
When installing the new Conveyor Drive
Motor Sprocket, be sure to engage the chain on
the motor sprocket and conveyor sprocket, then
adjust the tension on the chain to allow 4.763 mm
chain deflection as described in the procedure
DRIVE CHAIN DEFLECTION ADJUSTMENT in
the ADJUSTMENT Section, before tightening the
motor mounting plate screws.
Conveyor Drive Motor Capacitor
WARNING
DIsCONNECT THE ELECTRICAL
POWER TO THE BROILER AND
FOLLOW LOCKOUT / TAGOUT
PROCEDUREs.
1. Remove the Upper Lift Off Panel. Refer to the
COVERS and PANELS section of the manual.
2. Remove Lower Control Side Service Panel.
Refer to the COVERS and PANELS section
of the manual.
3. Disconnect wires to Conveyor Drive Motor
Capacitor.
4. Discharge the capacitor. Ground the two leads
to the broiler frame.
5. Remove screw securing capacitor to frame
and remove Conveyor Drive Motor Capacitor.
6. Reverse procedure to install a new Conveyor
Drive Motor Capacitor.
Conveyor
Drive Motor
Capacitor
Conveyor Drive Motor Capacitor