Operation Manual
Track Supply 6 kW
80 / 125 A at 400 / 480 V
BAL9100-0124c-EN
www.conductix.com
Page 35 of 44
17
Maintenance
All disassembly work has to be carried out by qualified staff (IEC 364 respectively. CENELEC HD 384 or DIN
VDE 0100 and IEC 664 or DIN VDE 0110 and national safety rules).
Qualified staff according to the safety regulations are a persons who are familiar with the installation,
assembly, commissioning and operation of the energy supply system and who have the appropriate
qualifications.
All maintenance/repair work have to be done according to the present operation manual. The specifications of
this document have to be strictly observed. In addition, national regulations and whenever they apply
regulations specific to the industry are to be taken into account.
Attention: Prior to starting maintenance work disconnect the Track Supply from the main supply!
During maintenance and repair work the Track Supply must be secured against unexpected and
unintended turn on.
The following maintenance work should be carried out at regular quarterly intervals:
•
Look for visible damage outside and check for any sign of damage due to the ambient conditions (i.e.
damage to the enclosures and covers due to spraying water, oil etc.).
•
Check that free in-coming and out-coming airflow is ensured. Verify that the air supply and the air outlets of
the Track Supply are not blocked by any objects.
•
Ensure the Track Supply is dry, clean and dust and oil free. If the Track Supply is obviously very dirty
reconsider the IP protection and contact Conductix-Wampfler for cleaning advice.
The following maintenance work should be carried out at regular yearly intervals. If operating conditions are
heavy and ambient is not clean shorter intervals must be chosen, recommendation is every 6 months at
maximum.
•
Consult Conductix-Wampfler to have qualified personnel check the operating parameters of the IPT
®
System. Have them compare measured values in the system with those obtained during commissioning or
during the last system check. Have them check free air flow inside the cabinet and specific torques.
Warning:
After having completed the maintenance work attach enclosure covers before restarting
the operation of the system. Improper attachment of the housing cover can cause severe
injuries to persons or damage to components.