Operation Manual
Track Supply 6 kW
80 / 125 A at 400 / 480 V
BAL9100-0124c-EN
www.conductix.com
Page 23 of 44
10
Installation
10.1
Who is authorized to carry out the installation?
All installation and commissioning work as well as maintenance work and disassembly have to be carried out
by qualified staff (IEC 364 respectively CENELEC HD 384 or DIN VDE 0100 and IEC 664 or DIN VDE 0110
and national safety rules).
All installation and commissioning work have to be done according to the present operation manual. The
specifications of this document have to be strictly observed. In addition, national regulations and whenever
they apply regulations specific to the industry are to be taken into account.
Qualified staff according to the safety regulations are persons who are familiar with the assembly and
installation of the energy supply system and who have the appropriate qualifications.
10.2
General advice for the installation
•
After receipt of the component(s) and prior to starting the installation work, unpack the component(s) and
check carefully for damage that may have occurred during transport or storage (damage to housings and
insulation, missing parts etc.).
•
Check data on the identification plate to make sure that the component(s) meet the requirements with
regard to nominal power and voltage.
•
Check completeness of the documents and conformity with the delivered component(s).
•
When operating several track supplies in one plant the control board may need to be synchronized.
Conductix-Wampfler provides documentation with the synchronization components.
For the installation of the Track Supply make sure that it is mounted safely. It has to be secured on site so that
the position of the Track Supply will be permanently safe!
An improper installation of the energy supply system has a negative effect on its function, efficiency and
lifetime. It is therefore important to observe the specification for the choice of the place of installation. The
guarantee will expire if this is not observed!