Commissioning
46
MAXXfl o EVO 150/302
5.2.4 HEAT ENGINE COMMISSIONING COMPLETION
•
Refi t fan PWM connector onto the top heat exchanger, then press the RESET toggle switch for 1 second
to clear the control lockout.
•
Once the lockout has been cleared from the display (bell symbol is not being displayed) close the door of
the heater and secure it with the two door clips.
•
Turn the operation switch to ON or “I” and wait for both heat engines to ignite and operate at maximum
output.
•
Keep the DHW tank temperature below 40
O
C (by opening water outlets). Check the total gas
consumption fi gure using the following table:
•
The gas consumption must be within 5% of the gross kW input value of the data plate
•
Turn off all taps and water draw off s.
•
Change the DHW Set-point to back to 60
O
C to 65
O
C as required by the user
•
Heat engine commissioning is complete
G20 GAS (38.8 MJ/m³)
Metric meter
Imperial meter
Model
gross kW
input
Time taken to consume
0.1m
3
of gas
Time taken to consume
0.5m
3
of gas
Time taken to consume
5ft
3
of gas
MAXXfl o EVO 150
149.9
25.0s (+/- 1.3s)
2m 5s (+/- 6.3s)
35.4s (+/- 1.8s)
Содержание 7800597
Страница 2: ...General 2 MAXXflo EVO 150 302 Blank Page ...
Страница 19: ...Technical Data 19 MAXXflo EVO 150 302 PCB2 3 6 WIRING DIAGRAM MAXXflo EVO 150 kW MODEL ...
Страница 86: ...Blank page ...
Страница 87: ...Blank page ...
Страница 88: ...April 2022 FM00866 EMS514880 13755 M10419 Rev A April 2022 ...