Benchmark 750/1000 Boiler
Installation, Operation & Maintenance Manual
CHAPTER 2 – INSTALLATION
OMM-0082_0J
AERCO International, Inc.
•
100 Oritani Dr.
•
Blauvelt, NY 10913
Page
17
of
192
GF-130
Ph.: 800-526-0288
05/21/2014
Figure 2-1b: BMK 750 & 1000 Anchor Bolt Locations
KEEP THE UNIT AREA CLEAR AND FREE FROM ALL COMBUSTIBLE
MATERIALS AND FLAMMABLE VAPORS OR LIQUIDS
.
While packaged in the shipping container, the unit must be moved by pallet
jack or forklift from the FRONT ONLY.
FOR MASSACHUSSETTS ONLY:
For Massachusetts installations, the unit must be installed by a plumber or
gas-fitter licensed within the Commonwealth of Massachusetts. In addition,
the installation must comply with all requirements specified in Chapter 1
(Safety Precautions), pages 11 and 12.
2.4.2 Setting the Unit
The unit must be installed on a 4 inch to 6 inch housekeeping pad to ensure proper condensate
drainage (see NOTE below). If anchoring the unit, refer to the dimensional drawings in Figure 2-
1b for anchor locations.
NOTE
When using the AERCO Condensate Neutralizer Tank for proper
condensate drainage, the Neutralizer Tank must be stored in a pit, OR the
boiler and AERCO Condensate Trap must be elevated higher than 4”
above the floor. See Condensate Tank instructions in TID-0074 for details.
After unpacking and inspecting the boiler, remove the four (4) lag screws securing the boiler to
the shipping pallet. The boiler can be lifted and moved by inserting forklift tines in the front slots
provided in the base of the unit, or it can be lifted by attaching a lifting bar to the unit’s heat
exchanger. A lifting bar (59174), with attaching hardware, is supplied with each unit. When
shipped, this bar is attached to the rear of the unit as shown in Figure 2-2, View A. One (1)
WARNING
CAUTION