Benchmark 750/1000 Boiler Installation, Operation & Maintenance Manual
CHAPTER 6 – SAFETY DEVICE TESTING
Page
86
of
192
AERCO International, Inc.
•
100 Oritani Dr.
•
Blauvelt, NY 10913
OMM-0082_0J
05/21/2014
Ph.: 800-526-0288
GF-130
Figure 6-4: Boiler Rear View Showing Air Inlet Location
6.9 SSOV PROOF OF CLOSURE SWITCH
The SSOV shown in Figure 6-1 contains the proof of closure switch. The proof of closure switch
circuit is checked as follows:
SSOV Proof of Closure Switch
1. Set the unit’s
ON/OFF
switch to the
OFF
position.
2. Place the unit in Manual Mode and set the valve position between 25% and 30%
3. Refer to Figure 6-3 and locate the SSOV.
4. Remove the cover from the SSOV by loosening the screw shown in Figure 6-5. Lift off the
cover to access the terminal wiring connections.
5. Disconnect wire #148 from the SSOV to “open” the proof of closure switch circuit.
6. The unit should fault and display
SSOV SWITCH OPEN.
7. Replace wire #148 and press the
CLEAR
button.
8. Set the
ON/OFF
switch to the
ON
position to start the unit.
9. Remove the wire again when the unit reaches the purge cycle and
PURGING
is
displayed.
10. The unit should shut down and display
SSOV FAULT DURING PURGE.
11. Replace the wire on the SSOV and press the
CLEAR
button. The unit should restart
.
Figure 6-5: SSOV Actuator Cover Location
SSOV ACTUATOR
COVER
ACTUATOR
COVER SCREW
SECONDARY WATER
INLET/RETURN
PRIMARY WATER
INLET/RETURN
EXHAUST MANIFOLD
AIR INLET
(Combustion Air
Duct removed)