112
System Manual SCK Gas Sampling System
42/23-81 EN Rev. 4
Overview: Start-up
Proceed as follows to start up the gas sampling system:
Step Procedure
Instructions
in
...
1
Check installation for proper
condition.
Installation check
on page
113
2
Fill cooling water and check
water-tightness of the cooling-
water circuit.
Preparing the cooling-
water circuit
on page 114
3
Check enclosed compressed-air
supply, fill oiler.
Preparing the com-
pressed-air supply
on
page 116
4
Switch on the gas sampling sys-
tem.
Activation
on page 118
5
After switching on: vent cooling-
water circuit.
After switching on: Work-
ing on the cooling module
on page 121
6
Check pneumatic system with the
aid of the compressed-air switch
in the pneumatic box.
Checking the pneumatic
system
on page 123
7
In the control cabinet: check
frequency converter settings and
correct if necessary.
Checking frequency con-
verter settings
on page
124
8
Check operating parameters of
the gas sampling system and
correct if necessary.
Checking/correcting oper-
ating parameters
on page
127
9
Only if using probe H:
check current monitoring relay
settings.
Check probe heating power
supply.
Checks to perform when
using probe H
on page
128
10
Insert the probe for the first time,
then adjust the speed of the
probe during operation, adjust oil
delivery rate on the compressed-
air oiler, and check direction of
rotation of the heat exchanger.
Inserting the probe and
switching to automatic
mode
on page 131
Instructions
Содержание SCK
Страница 2: ......
Страница 16: ......
Страница 36: ......
Страница 54: ......
Страница 110: ......
Страница 222: ......
Страница 232: ......
Страница 234: ...234 System Manual SCK Gas Sampling System 42 23 81 EN Rev 4 Pneumatic hydraulic interface plan ...
Страница 235: ...42 23 81 EN Rev 4 System Manual SCK Gas Sampling System 235 ...
Страница 236: ...236 System Manual SCK Gas Sampling System 42 23 81 EN Rev 4 Electrical connection plan ...
Страница 237: ...42 23 81 EN Rev 4 System Manual SCK Gas Sampling System 237 ...
Страница 238: ...238 System Manual SCK Gas Sampling System 42 23 81 EN Rev 4 Transformer connection plan ...
Страница 242: ......
Страница 243: ......