Chapter 11. 3DM 2 Reference
202
3ware Serial ATA RAID Controller User Guide
Follow Schedule/Ignore Schedule.
You can enable or disable the schedule
for the Rebuild/Migrate and Verify tasks by selecting either
Follow Schedule
or
Ignore Schedule
. When schedules are set to be ignored, these tasks can be
performed at any time, and are not restricted to the scheduled times.
For details about the different background tasks, see “Background Tasks” on
page 147.
Task Schedules
Initially, 7 schedule slots are defined, for 24 hours each. Even if
Follow
Schedule
is enabled, this schedule is equivalent to
Ignore Schedule
, because
tasks can run at any time, round the clock.
A maximum of 7 slots can be created, so to set a different schedule, start by
deleting one or more of the existing scheduled slots, and then add new slots.
For step-by-step instructions for adding and removing schedules, and setting
schedules to be followed or ignored, see “Scheduling Background Tasks” on
page 161.
Self-test Schedules
Unlike scheduling of rebuilds and verifies, scheduling of self-tests is always
followed. To disable self-tests you either remove all schedule times, or
uncheck the tests listed in the Tasks column.
Two self-tests can be scheduled:
Upgrade UDMA mode.
This test checks the speed at which data transfer to
drives is occurring, to see if the UDMA mode can be increased. (If you are
already running at the fastest UDMA mode, then this self-test has no effect.)
Note:
Scheduling of these tasks is only available on the 9000-series controllers.
Note:
Only the checked tasks will be run during the scheduled times. If none of the
tasks are checked, self-tests will never run, even if you have scheduled time slots
set.