![YASKAWA Solectria PVI 25TL-208 Installation And Operation Manual Download Page 114](http://html1.mh-extra.com/html/yaskawa/solectria-pvi-25tl-208/solectria-pvi-25tl-208_installation-and-operation-manual_3491610114.webp)
Installation and Operation Guide SOLECTRIA® PVI 25TL-208, PVI 50TL-480 and PVI 60TL-480
DOCR-071030-A (10/7/2022)
Page 114 of 131
o
Torque value: 1.6N.m (14.2in-lbs)
Figure 8-6 Install the cover on the connector of the Wiring Box
INFO
✔
The cover connector does not provide a watertight seal – if inverter replacement is not immediately available,
additional methods of waterproofing the wire box shall be provided by the installer.
Uninstall the Inverter
Uninstall the inverter and wiring box assembly according to the following steps when the inverter needs to be
removed:
Turn off the external AC breaker and/or system disconnect switch using lock-out/tag-out procedures.
Turn off the external DC breaker and/or disconnect switch, if present, and use lock-out/tag-out
procedures. (Skip this step if there is no DC circuit breaker.)
Switch the inverter’s AC disconnect switch to “OFF” position.
Switch the inverter’s DC disconnect switch to “OFF” position.
Wait for 5 minutes to ensure the internal capacitors have been completely discharged.
Measure the AC output conductor terminal voltage against the ground. The meter should now read 0V.
Disconnect the AC and EGC cables referring to “3.3.4 Electrical Installation AC”.
Disconnect the DC cables referring to “3.3.3 Electrical Installation DC”.
CAUTION
Energized conductors
•
If PV strings terminate directly into the wiring box and do not pass through a breaker or switch that was
opened in Step 2 of Section 8.2 Uninstall the Inverter, these homerun conductors may be energized.
Uninstall the inverter by reversing the installation steps found in section 3.2 Mechanical Installation