Stationary Sawmill Setup
Set up the mill on firm footing and level by eye. Fasten the mill to the floor to prevent any creep after prolonged
use. A cement pad with 5/8” diameter anchor bolts is recommended. The cement pad should be rated to sup-
port 31 T/m
2
at each sawmill foot position.
NOTE:
Make sure the unit is level before securing. It IS possible to twist the mill frame by jacking one foot
higher than the others.
Level the sawmill by adjusting the feet to raise or lower each end of the sawmill. Adjust all feet evenly to avoid
twisting the mill frame by jacking one feet higher than the others.
WARNING!
Securely fasten the feet of a stationary sawmill to the floor
before operating the sawmill. Failure to do so may result in serious injury or
death.
See Figure 2-1.
FIG. 2-1