13.Advice of acceptance test
Lift controller of STEP Sigriner Elektronik GmbH are manufactured and checked with EN81 and VDE-
standards. The used components, especially the main- and auxiliary contactors are selected respectively to
the requirements of EN81, VDE0100, VDE0660.
All adjustable components, like engine-security-switch,frequency inverter etc. are allready pre-adjusted by us as
far as possible. It is incumbent upon the installing company to adjust these components before implementation
with respect to the resources..
By default the security cycle is fused with a power protection switch withF2 (2A Charakteristik C).
As amaximum a power protection switch with 4A can be used.
Generally
Keep doors closed:
To check troublefree the doors could be blocked withF165 bit1=1
Inspection run:
has always priority before return motion and it is also possible with activated
return motion control. The by-pass of the security switch is deactivated. With
F76 and F77 virtuell inspection-end-switches could be set. This to avoid that
accidently the fold support in the fosse are overrunned. As soon as the shaft
copying isn't completly engaged set bith values on „0“. within the doorzone with
AUF/ Zu button the function of the doors could be checked. Otherwise during
inspection run doors are always closed.
Return motion run:
this is only possible with deactivated inspection control. Appropriate security
switches, like emergency-end-switch, arrester-switch etc. will be by-passed. The
return motion is also stopped by the virtual inspection end switches F76/77.
Cabin light:
If failure of cabin light ( simulation F02) the lift stops at next floor and door
opens.
Motor temperature
A PTC switch-OFF leads as well to a shut down at the next possible stop.
Isolation measurement:
By default the controller undergo a isolation masurement in the factory. The IN-SITU arranged measurement
refers only to the connected ressources of the lift
Please respect imperativly the safety regulations while executing this procedures. There is danger for limb
and life !
In order to avoid damages of the controller, switch off the respective fuse F2 at the controller for measurements.
Connection of frequency inverter, USV-systems and other systems with power semiconductors and filter,
most likely have to be disconnected or hot-wired according to manufacturers for testing purpose. For this
follow the advises of the manufactures.