Installation and operating instruction
Gas condensing unit WTC-GB 15-B Compact and WTC-GB 25-B Compact
3 Product description
83309302 1/2018-05 La
17-196
O
2
correction
Following calibration via the output measurement or using the commissioning wiz-
ard, a new O
2
curve is generated.
The entire curve can then be moved in parallel via the
O2 total correction
at max load, thus optimising the O
2
content; the WTC drives to 100 % capacity.
Using
O2 correction up to 50%
at min load the O
2
content can also be
optimised in the lower load range.
Example
5.2
5.1
5.0
4.9
4.8
4.7
4.6
4.5
5.3
5.4
2
1
3
4
7
6
5
1
Burner capacity
2
O
2
content [%]
3
minimum load
4
maximum load
5
O
2
curve following calibration
6
O
2
curve following
O2 total correction
at max load
7
O
2
curve following
O2 correction up to 50%
at min load