Installation and operating instruction
Gas condensing unit WTC-GB 15-B Compact and WTC-GB 25-B Compact
7 Commissioning
83309302 1/2018-05 La
102-196
7 Commissioning
7.1 Prerequisite
Commissioning must only be carried out by qualified personnel.
Only correctly carried out commissioning ensures the operational safety.
Prior to commissioning ensure that:
all assembly and installation work has been carried out correctly,
the appliance and heating system have been filled with media and vented,
the siphon has been filled with water,
an adequate supply of fresh air is guaranteed,
flue gas ducts and combustion air ducts are unimpeded,
all regulating, control and safety devices are functioning and set correctly
a heat demand is available
Additional system-related tests could be necessary. Please observe the operating
guidelines for the individual components.