Cotter Corporation (N.S.L.)
Cañon City Milling Facility
Cañon City, Colorado
Procedure
Field Global Positioning
System Surveying
Number: SOP-E-140
Page: 6 of 7
Revision: 1
Date: May 2016
9.6.1
Data
icon on toolbar.
9.6.2
Select Points.
9.6.3
Select Listing.
9.6.4
Select the measurement taken from the known control panel point survey.
Compare the elevation and coordinates recorded to the known
measurements listed on the reference sheet.
9.6.5
If the survey measurements are within the expected tolerance system is
ready for use.
9.6.6
If the survey measurements are outside of the expected tolerance range,
recheck the setup parameters in the FC-200 data collector.
9.6.6.1
This could be caused by survey rod not centered on panel point
pin.
9.6.6.2
Incorrect rod height entered in FC-200 data collector.
9.6.7
Re-survey control panel point and compare measurements to the known
elevation and coordinates listed on the reference sheet.
9.7
Proceed to requested location(s) for survey measurements.
9.8
At the requested location for survey, attach rover receiver to survey rod.
9.9
Verify data collector and receivers are communicating by noting the icon on the
FC-200 data collector is green.
9.10
On the FC-200 data collector screen select:
9.10.1
Survey
icon on toolbar.
9.10.2
Measure pts.
9.10.3
Topo-shot.
9.10.4
Input a description for survey point.
9.10.5
Press enter, data collector will indicate when measurement is completed.
9.11
Proceed to next location.
9.12
When surveying is completed return to base station location.