Installation and Configuration Task Overview
530-0267-00 Rev 02
7700 Flash Storage Platform Installation Guide 7.6.3.x
7.6.3
21
Installation and Configuration Task Overview
This section provides an overview of the 7700 FSP hardware installation, cabling, and configuration
tasks in the recommended order. The related reference documentation is listed in the Table 1.9
Task
Description
Task 1:
Unpack, inspect contents of all 7700 FSP device shipping boxes, and
rack mount all 7700 FSP components including the Fibre Channel
switches. For details, see
on page 24 for related
reference documents.
Note:
Ensure that you properly ground all shelves installed in the
rack. For details, see the latest version
7000 Series Flash Storage
Platform Installation Guide
or
6000 Series All Flash Array Installation
Guide
.
Note:
For details on the best practice for rack-mounting storage
shelves, see
on page 17. For more details, see
equipment racks in the latest version
7000 Series Flash Storage
Platform Installation Guide
.
Task 2:
Install Symphony, connect all storage network, management network,
and power connections to the 7700 FSP components. For details, see:
•
Connecting Cables to the Fibre Channel Switches
•
Connecting Cables to the Fibre Channel Switches
•
Connecting 7700 FSP Cluster Storage Devices
•
Connecting Northbound Fibre Channel Ports
•
Connecting Northbound iSCSI Cables
•
Powering on the 7700 FSP Devices
Task 3:
Configure shelves for the 7700 FSP system, the 7700 FSP Controllers,
the fibre channel switches, and manage the FC switch zone
configuration. For details, see:
•
Configuring 7700 FSP Storage Shelves
•
Configuring the 7700 FSP Controller
•
Configuring Brocade 6510 Fibre Channel Switches
•
•
•
Understanding a Fibre Channel Switch Zone
•
Managing the Zoning Configuration
Table 1.9 7700 FSP Hardware Installation, Cabling, and Configuration Tasks