69
3.
Fit flange cover
B
and tighten eight
screws
D
with a maximum torque of
25 Nm.
4.
Push earth cable
C
onto the tab.
5.
Fit cover
E
.
6.
Fill the primary store with potable
water.
Checking the diaphragm expansion vessel and system pressure
A
Note
(GB only) The diaphragm expansion
vessel can lose some charge pressure
over a time in use. When the boiler heats
up, the pressure gauge will indicate a
higher pressure of 2 or 3 bar (0.2 or
0.3 MPa). The safety valve too can
respond and discharge excess pres-
sure.
Check whether the installed diaphragm
expansion vessel is adequate for the
system water volume. (GB only)
Note
Carry out this test on a cold system.
1.
Drain the system until the pressure
gauge shows "0".
2.
If the diaphragm expansion vessel
pre-charge pressure is lower than the
static system pressure: Top up with
nitrogen at connection
A
until the
pre-charge pressure is 0.1 to 0.2 bar
(10 to 20 kPa) higher than the static
system pressure.
3.
Top up with water until the charge
pressure of the cooled system is 0.1
to 0.2 bar (10 to 20 kPa) higher than
the pre-charge pressure of the dia-
phragm expansion vessel.
Permiss. operating pressure: 3 bar
(300 kPa).
Commissioning, inspection, maintenance
Further details regarding the individual steps
(cont.)
5773 238 GB
Service
Summary of Contents for B2UA
Page 10: ...10 13 14 15 Preparing for installation Preparing the installation cont 5773 238 GB ...
Page 11: ...11 16 Preparing for installation Preparing the installation cont 5773 238 GB Installation ...
Page 12: ...12 sF 17 19 21 20 18 Preparing for installation Preparing the installation cont 5773 238 GB ...
Page 14: ...14 27 26 25 Preparing for installation Preparing the installation cont 5773 238 GB ...
Page 41: ...41 2x 1 4 2 3 5 Installation sequence Fitting the front panels 5773 238 GB Installation ...
Page 199: ...199 5773 238 GB ...