Commissioning
Before commissioning the control panel
Before commissioning the control panel, make sure that:
• The control panel has been correctly installed.
• The mains power is 110 VAC or 240 VAC, is connected correctly, and
complies with all requirements described in “Connecting the mains power
supply” on page 17.
• There are no short or open circuits in any of the zones.
• All zones have the correct end-of-line termination, as described in
“Terminating zones” on page 8.
• All extinguishing devices (with special attention to the extinguishing actuator)
are properly installed as described in “Connections” on page 7. Ensure that
the polarity is correct and that the correct end-of-line is fitted if it is required.
Note:
Observe the polarity of the extinguishing actuator output to ensure
proper operation.
WARNING:
Risk of death or severe injury. Test the line supervision (for open
and short circuit faults) and the activation function
before
connecting the
extinguishing agent to the actuator.
• Any optional equipment is correctly connected. This includes fire detection
devices, fire routing, alarm and fault relays, etc.
• The batteries are connected correctly, and comply with all requirements
described in “Connecting the batteries” on page 18.
• All system configuration complies with the corresponding operating mode and
local regulations.