Underground power in conduit:
When power cabling is provided from
an underground foundation it enters the
Veefil through the baseplate conduit hole
as shown in Figure 1 and Figure 2.
Figure 2.
When preparing the foundation, allow
approximately 1 metre/ 3 feet of conduit
and wiring from the foundation surface as
shown in Figure 3.
Figure 3.
1 metre
3 ft
Above ground power in conduit:
Electrical requirements:
Supply current:
Worldwide (excluding USA):
80A
USA only:
63A
Conduit fittings:
Worldwide (Excluding USA):
Use 40mm flexible conduit, or Flexa
system:
Flexa PN 0237.202.036 conduit
Flexa PN 5020.037.250 conduit fitting
Flexa PN 0333.000.040 sealing washer
Flexa PN 0561.000.040 locking ring
USA Only:
Flexa PN 0237.202.036 conduit
Flexa PN 5020.056.207 conduit fitting
Flexa PN 0331.001.008 sealing washer
Flexa PN 0531.000.006 locking ring or 1
1/4” metal locking ring
Communications:
3G network capability or Ethernet.
Ethernet cable
(if required)
Worldwide (Excluding USA):
Use 20mm flexible conduit.
USA Only:
Use ENMT Schedule 40 PVC 3/4in
conduit.
Power supply preparation:
The Veefil is designed to accommodate
power cabling in two different scenarios;
through an underground conduit, or with
conduit above the ground. Refer to the
installation instruction for full details on
installation and commissioning.
Site Configuration & Fixing