INSTALLATION NOTES
General Installation information can be obtained from Techsys Corporation regarding the
site-specific requirements however
there are some “GOLDEN RULES” in site installation
that should be followed.
Site Installation
•
Standard SWO requires a NEUTRAL
•
Select the site most shaded and out of direct sunlight.
•
Allow the airflow from the fans to be unimpeded.
•
The earth needs to be close and not laid parallel with High Voltage cables
Inputs
•
Use shielded wire for all inputs
•
Connect the shield to EARTH and one end only
•
Never apply voltage to the Inputs
•
Take care in running inputs for long distances
•
The inputs use a 24VDC signal as the carrier voltage- use compliant
sensors.
Outputs
•
5 amp maximum switching load
•
Check the programming on each output before trying to troubleshoot
Start-up
•
CHECK ROTATION
•
Calibrate transducer
•
Input level settings
All these items are site related.