Preventive Maintenance Schedule
Preventive Maintenance Schedule
Table
is the preventive maintenance schedule for the Con-
ductor VMS Series 43 Auxiliary Terminal. The table lists the
preventive maintenance tasks in groups according to their
specified maintenance interval. Some tasks in Table
are
self explanatory. Instructions for tasks that require further
explanation are found in the procedures or in the manufac-
turer’s documentation supplied with the workstation.
Table 5-1. Preventive Maintenance Schedule
Task
Procedure
Frequency
General cleaning, including, but not limited to:
Monitor
Printed circuit boards
Keyboards
As required
With power on, be sure fans are turning. With power off, wipe dust off
all fan blades.
N/A
1 month
Check cabinet and modules for dust. Clean as necessary using an anti-
static vacuum.
N/A
3 months
Check power supply outputs. Adjust power supplies if needed.
Clean CD ROM drive
1
N/A
Check the air filters. Clean or replace them as necessary. Check the air
filter more often in excessively dirty environments.
N/A
6 months
Check all signal, power and ground connections within the cabinet and
verify that they are secure.
Check the quality of the plant power and grounding system. Follow the
power and grounding system verification procedures in
N/A
12 months
Inspect and check the PEP. In high vibration environments testing may
be necessary at shorter intervals.
2 years
Replace power supplies. Call Elsag Bailey sales and service for
information.
Figure
5 years
Complete all appropriate tasks in this table.
N/A
Shutdown
NOTE:
1. Perform this procedure by following the manufacturer’s instructions.
Summary of Contents for C-I-CV43C
Page 1: ...Bailey Hartmann Braun TM Instruction Conductor Conductor VMS Series 43 Auxiliary Terminal...
Page 13: ...WBPEEUI220772A0...
Page 23: ...WBPEEUI220772A0...
Page 37: ...WBPEEUI220772A0...
Page 47: ...WBPEEUI220772A0...
Page 49: ...WBPEEUI220772A0...
Page 57: ...WBPEEUI220772A0...
Page 61: ...WBPEEUI220772A0...
Page 75: ...WBPEEUI220772A0...
Page 87: ...PR6 4 WBPEEUI220772A0 Procedure Figure PR6 3 CPU Input Voltage T00440A REAR OF CPU 230 V 115 V...
Page 93: ...WBPEEUI220772A0...
Page 103: ...WBPEEUI220772A0...
Page 109: ...WBPEEUI220772A0...
Page 117: ...WBPEEUI220772A0...
Page 121: ...WBPEEUI220772A0...
Page 123: ...WBPEEUI220772A0...
Page 125: ...WBPEEUI220772A0...
Page 129: ...WBPEEUI220772A0...
Page 131: ...PR25 2 WBPEEUI220772A0 Procedure Figure PR25 1 Multibus Card Cage T01448A FRONT VIEW SCREWS 4...
Page 139: ...PR28 4 WBPEEUI220772A0 Procedure Figure PR28 2 PEP Replacement T01308A FRONT VIEW SCREWS 5...
Page 151: ...WBPEEUI220772A0...
Page 153: ...WBPEEUI220772A0...
Page 159: ...WBPEEUI220772A0...
Page 169: ...WBPEEUI220772A0...
Page 173: ...WBPEEUI220772A0...